The general building package for the aseptic facility expansion for Pfizer consists of various construction work to the following new buildings:
Production building Warehouse Central utilities building Waste management facility Security building Personal support building and link to new production building Refurbishment of existing operational Pfizer production building
The construction works to the above buildings consist of the following:
Excavation, backfilling and disposal Pile caps, ground beams, pad and strip foundations Retaining walls Slab on grade and suspended floor slabs Syphonic and gravity drainage systems Interior wall and ceiling finishes Floor finishes Internal doors Refurbishment and maintenance works within the live facility General site works
Project Details:
Client: Pfizers Location: Pottery Road, Dun Laoghaire, Co. Dublin Consultants: Jacobs Engineering Project Value: € 26 Million Completion Date: August 2007