Projects
1-Ballynagran
Construction of 5 No lined Cells included the following;
350,000m3 of earthworks excavation.
Process (Screen) and lay 50,000m3 of boulder clay liner to Cells.
Lay 50,000 m2 of 2mm HDPE liner, geocomposite drainage membrane and geotextile.
Install Pumped Sub Cell drainage system.
Install Leachate drainage system to include 30,000 tonnes non calcareous drainstone.
Construct Surface Water Storage Lagoon to include 7500m2 HDPE and Clay liner.
Perimeter Fence - 4200lin.m.
Construct access roads and tracks - 1500 lin.m
|
|
| Project Details: |
Client: Greenstar
Location: Coolbeg, Co. Wicklow
Consultants: SLR Consulting, Wiltshire
Project Value: € 8 Million
Completion Date: December 2007
|
|
| |
|
|